PROJECT: Homs Sewage Treatment Plant

Customer: Ministry of Housing & Utilities ( MHU )

Funding : Arab Fund for Social and Economic Development /Kuwait/

Start date: 1994

Status: Completed on June 2001

Project Description
Scope of works: Supplying & installing the mechanical and electrical equipment for the waste water treatment plant of Homs
Process: Conventional Activated Sludge
Average flow: 135.000 m3/day
Capacity : 750.000 P.E

Contractor:

SEE/I Kruger Engineering with Electro Scientific Office ( ESO )
Value: approx. 14 Million US$ plus
30 Million Syrian Pounds for relative local works.

Civil Works: By a separate contract under the supervision of CEC engineers .
Contractor: The General Company for Irrigation and Drinking Water project /Rima/
Value: approx. 200 Million Syrian Pounds

The project consists of 3 phases
1 - Phase A: Supply and erection of the mechanical & electrical equipment :
Works have completed by mid December 1998
Works have been taken over in March 2000
The Performance Bond has been released after the defect reliability period
Retention of 10% also has been released without any deduction


2 - Phase B: Operation & Maintenance period ( man/month basis ):
Operation & Maintenance works have been performed by CEC staff and the support of SEE/I Kruger .
The works have been taken over in June 2000 .
3 - Phase C: Technical Assistance period ( man/month basis ):
Training works and Technical Assistance were performed professionally by CEC engineers for a period of 18 man/month. These works included the following:
Training on the electrical & mechanical equipment
Training on the operation of the complete plant.
Training on the maintenance of each facility of the plant.
Training on security and industrial safety.
 
 

Works have been completed in June 2001
The project was implemented successfully by SEE/I Kruger for which ESO was the sub-contractor for all relative local works, such as : erection of the mechanical & electrical equipment, testing & commissioning, operation & maintenance, technical assistance & training and supply of chemicals.

The SEE/I Kruger has had a very good reputation in the Syrian territories as a very competent contractor for water and environmental projects especially after issuing the final taking over certificate.
Thanks to the skillful and serious follow-up performed by our staff in all aspects (technical, administration, and financial ). The contract was completely executed with all its requirements and met the satisfaction and acceptance of the concerned authorities.

The other projects

PROJECT: Hama Sewage Treatment Plant

PROJECT : Supply of Steel Pipes and fittings for ain al Zarqa - Lot 6

PROJECT: Supply & Erection of mechanical & electrical equipment for REDRYING factory of tobacco

Our Projects