Customer:
Ministry of Housing and Utilities
Funding: Arab Fund for Social and Economic Development
/Kuwait/
Start date: April 1999
Status:
Material
being delivered 100%
Installation
of mechanical equipment 90% completed up to March 2003.
Installation
of electrical works 60% completed up to March 2003 .
The remaining
works to be completed by the end of September 2003 according to
civil works' progress .
Project Description:
Scope
of works : Supplying & Installing of the mechanical and
electrical equipment for Hama Sewage Treatment Plant, as well
as the works of operation , maintenance , technical assistance
and training.
Process:
Conventional Activated Sludge
Maximum
flow: 85,000 m3/day
Pumping
station 1700 L/sec. and 38 m elevation .
|
|
|